38
999805002 - 09/2018
Horizontal assembly
User Information
Load-bearing tower Staxo 40
Lifting into the upright by crane
➤
Check before attaching the crane suspension tackle:
Lifting into the upright
➤
Attach the crane suspension tackle to the frames of
the top section and lift the entire tower into the
upright.
➤
Observe the crane-slinging details given in the sec-
tion headed 'Lifting by crane'!
▪
All Staxo 40 tube connectors D48.3mm
must be in place (to link the frames).
▪
All screw-jack head and base units must
be secured against drop-out.
▪
All safety catches must be closed.
NOTICE
▪
Max. height of the tower unit to be lifted into
the upright: 11
m
▪
Max. weight of the tower: 700
kg
▪
Max. extension length of the screw-jack
base units when the tower is being lifted into
the upright: 30
cm!
NOTICE
▪
Erect the load-bearing tower in the vertical
on ground that is statically capable of sup-
porting the load.
▪
If the load-bearing tower is over 6
m high,
back-stay it or combine it with other towers.
980
-01
24-221
When the tower is standing in the upright,
check once again to make sure that all the
safety catches are closed.
Detaching the crane suspension tackle
near ground level:
This method must not be used for
placing the
tower back on its side
!
Items needed:
▪
3 x Scaffolding tube 48.3mm
(G)
- Minimum length:
Inter-frame space + 1.00
m
▪
6 x Screw-on coupler 48mm
95
(H)
▪
4 x Staxo 40 frame strut 1.40m
(I)
➤
Mount Staxo 40 frame struts in the bottom
and top 'storeys'
➤
Attach scaffold tubes:
- one to the bottom frame strut
- two to the top frame struts
➤
Attach two cables, chains or lifting straps to
the bottom scaffold tube.
➤
Lead the cables, chains or lifting straps
along the outside of the tower and between
the top scaffold tubes.
After the tower has been lifted into the upright,
the cables, chains or lifting straps are
detached by a crewman working from ground
level.
98024-221-02