7
|
Installation
Installer reference guide
99
C08AF + EHYKOMB33A
Daikin Altherma R Hybrid
4P471761-1E – 2020.10
Hatches must be a minimum of 300 mm×300 mm and positioned with the edge of
the inspection hatch to 1.5 m of any joint and at changes of direction. Bends
should be viewable from both directions where the inspection hatch cannot be
positioned at the bend.
Where suitable access is not provided the appliance must NOT be commissioned
and must be disconnected from the gas supply.
Additionally the entire flue and all flue seals must be installed in accordance with
the requirements of BS5440:
▪
Check if the condensate trap is filled with water and correctly connected to the
boiler.
▪
All flue joints are correctly made, unstressed and adequately supported.
▪
All parts of the flue can be visually inspected. Ensure suitable access where flue is
positioned within voids.
7.13 Finishing the outdoor unit installation
7.13.1 To finish the outdoor unit installation
NOTICE
It is recommended that the refrigerant piping between indoor and outdoor unit is
installed in a ducting or the refrigerant piping is wrapped with finishing tape.
1
Insulate and fix the refrigerant piping and cables as follows:
g
b
a
f
e
c
d
a
Gas pipe
b
Gas pipe insulation
c
Interconnection cable
d
Field wiring (if applicable)
e
Liquid pipe
f
Liquid pipe insulation
g
Finishing tape
2
Install the service cover.
7.13.2 To close the outdoor unit
See the outdoor unit installation manual.
7.14 Finishing the indoor unit installation
7.14.1 To close the indoor unit
1
Close the switch box.
2
Mount the side plate to the unit.
3
Mount the top plate.