Sea Tel Tracker 6000
2.
Apply a bead of caulking to the left and top flanges of panel 302. Set panel 302 in
place under 202 and loosely install the vertical & horizontal flange mounting bolts and
washers. Apply Loctite to the exposed threads of the bolts and tighten to torque spec
the bolts. Install a lifting strap on the bottom bolt between these panels. Wipe off the
excess caulking from inside and outside of the panel flanges.
3.
Repeat step 2 to mount panels 303-312. Install a lifting strap on the bottom bolt
between panels 304 & 305, 307 & 308 and 310 & 311.
4.
Set the radome assembly down on the concrete and relocate the 4-part lifting sling to
the lifting straps around the base of the third layer of the radome.
5.
Lift the radome assembly about 6 feet to allow installation of the fourth layer of the
radome under the third section.
3.3.8.
Assembling the Fourth Layer of the Radome
With the third section of the radome suspended, start assembling the fourth layer panels
(serial numbers ending with 401-412) of the radome by bolting them to each other and to the
panels above. They are numbered to assure that they are assembled in the correct order
(401 is mounted to the bottom of 301, etc).
1.
Set panel 401 in place under 301 and loosely install the horizontal flange mounting
bolts and washers. Apply Loctite to the exposed threads of the bolts, and with the
flange open apply a bead of caulking between the panels. Assure that panel 301 is
centered on panel 301 and tighten to torque spec the bolts. Wipe off the excess
caulking from inside and outside of the panel flange.
2.
Apply a bead of caulking to the left and top flanges of panel 402. Set panel 402 in
place under 302 and loosely install the vertical & horizontal flange mounting bolts and
washers. Apply Loctite to the exposed threads of the bolts and tighten to torque spec
the bolts. Install a lifting strap on the bottom bolt between these panels. Wipe off the
excess caulking from inside and outside of the panel flanges.
3.
Repeat step 2 to mount panels 403-412. Install a lifting strap on the bottom bolt
between panels 404 & 405, 407 & 408 and 410 & 411.
4.
Set the radome assembly down on the concrete and relocate the 4-part lifting sling to
the lifting straps around the base of the third layer of the radome.
3‐7
EAR Controlled - ECCN EAR99
Содержание Sea Tel Tracker 6000
Страница 8: ...SeaTelTracker6000 This Page Intentionally Left Blank viii EAR Controlled ECCN EAR99...
Страница 12: ...SeaTelTracker6000 Safety This Page Intentionally Left Blank 1 2 EAR Controlled ECCN EAR99...
Страница 16: ...SeaTelTracker6000 Site Survey Land Based This Page Intentionally Left Blank 2 4 EAR Controlled ECCN EAR99...
Страница 38: ...SeaTelTracker6000 Setup Testing This Page Intentionally Left Blank 4 2 EAR Controlled ECCN EAR99...