Available power
Note:
This parameter is required in the
Peak Shaving
strategy; it does not have to be pro
-
grammed in all other strategies.
This parameter is used to program the contracted power of the installation; with the
Peak Shav-
ing
strategy, the unit compensates the consumption peaks above this value, provided that the
energy available in the system (solar panels or battery) allows this to be performed.
Charge from grid enabled
When the enable charging from the grid option is selected, the unit allows you to program the
parameter:
Maximum grid charge power
Maximum grid charging value of the power that can be consumed in the installation.
With the
Peak Shaving
strategy, this value must always be lower than the contracted power.
Includes the consumption of direct loads connected to the AC output, consumption of indirect
loads and consumption of
CirPower Hyb
to charge the battery from the grid.
Note:
The
charge from grid
option can be disabled by default, depending on the selected type
of installation and strategy.
Step 7.- Configuration of the battery charging period and SOC target
If you have selected the
Peak Shaving
strategy, the battery charging period and SOC target
setup screen will be displayed,
Figure 40
.
Figure 44: Energy management strategy (Battery charging period)�
Programming these parameters will disable the option of charging the battery from the grid, if:
- The battery charging period is out of the programmed charging time period.
- The objective SOC has been reached.
Start hour
and
End hour
These parameters are used to configure the time interval during which the battery can be
40