Reports
17.1 Start-up report
Put your signature and the date at the bottom of the
start-up report.
Start-up activities
Page
Measured values
Remarks
1. Fill the heating system and check that all connections are tight
– Inlet pressure of expansion tank (observe the Installation Instructions
for the expansion tank)
– Pressurize the system
– Fill the condensate trap
27
27
27
27
__________ psi
__________ psi
2. Carry out a gas tightness test
27
3. Note down the gas characteristics:
Wobbe index
Operating heat value
27
__________ kWh/m³
__________ kWh/m³
4. Vent the gas supply conduit
29
5. Check and if necessary adjust the carbon monoxide content (CO
2
)
__________ %
6. Check the combustion air/flue gas connection
30
7. Convert the appliance to another type of gas supply (only if allowed)
86
8. Measure the gas connection pressure (flow pressure)
30
________ inch W.C.
9. Check and adjust the gas/air ratio
31
________ inch W.C.
10. Measure the pressure on the testing nipple on the burner cover
________ inch W.C.
11. Measure the pressure in the flue pipe
________ inch W.C.
12. Measure the carbon monoxide content (CO)
33
__________ ppm
13. Check and if necessary adjust the carbon monoxide content (CO
2
)
__________ %
14. Make the necessary settings on the thermostat
36
15. Carry out function testing
33
16. Measuring the ionization current
33
__________ µA
17. Fitting the casing
35
18. Inform the owner; hand over the technical documents
35
Confirm proper start-up
Company stamp/signature/date