4. Taking into operation
Barco – OverView cDG67-DL – R5976624– installation manual – Revision 03 – August-2005
______________________________________________________________
4-22
4
Taking into operation
4.1
Running the fans
Before taking the system into operation it must be
ensured that the fans and the hoses are dust free.
Therefore remove again the hoses from the
illumination unit and the projection unit and start
the fan.
Run the system in standby! Do not switch on the
lamps!
The fans should run for about 5 minutes before
continuing. Then re-attach the hoses.
Now you can start with the adjustment procedure.
OP01
4.2
Inserting the Lamp Modules
OP02
Fetch the lamp module on its housing. The
power socket is on the right side.
OP03
Insert the lamp carefully. Take care that the
"tubes" slide on the guide rods [2].
OP04
Mind the position of the fingers: the force is
to apply on the outer part of the module