Door Slide Rails:
Middle Level
(2) Door Slide Rails
(prefabricated)
(2) 19” Door Screen Units
(fabricated earlier)
(6) 1 5/8” Screws
(Three per Door Slide Rail)
(4) 3” Screws
(Two per Door Slide Rail)
Door Slide Rail installation continues. In this section, the two middle level Rails are installed onto the
middle Core Square. The process is almost identical to the previous section, so please reference “Door
Slide Rails: Lower Level” for the details of marking, drilling, and fastening.
Important:
To make the photographs in this section clearer, the fixed screens and panels were
removed. When building your coop, two of the sides will have the fixed screens and panels installed.
Rotate the coop so that an open side is facing you. (A side
where you have just installed the lower Door Slide Rail.)
Take one of the 19” Screen Door units and place it inside
the “slot” of the Lower Door Slide Rail.
Place one of the Door Slide Rails on top of the Screen
Door.