Operation
112
Citan BAG0014.4 09.14
10.7
Emptying the seed hopper and/or seed dosing unit
10.7.1
Emptying the seed hopper
1. Secure the tractor and the machine against
unintentional start-up and rolling before any
intervention in the machine.
2. Open the slider (Fig. 120) and empty the
seed into the calibration trough or a suitable
hopper.
Fig. 120
A commercially available hose (DN
140) can be fitted.
3. Empty the residual seed
(see also page 112).
10.7.2
Emptying seed dosing unit
1. Secure the tractor and the machine against
unintentional start-up and rolling before any
intervention in the machine.
2. Secure the calibration trough(s) under the
dosing unit(s).
Fig. 121
3. Close the shutter (Fig. 122/1) if only the
metering unit and not the seed box should
be emptied (see Seite 78).
Fig. 122