GASGUARD
®
TE10 Distribution System Manual
Air Products and Chemicals, Inc.
10 - 6
10.3 Safety Interlock Maintenance
The following maintenance should be performed to verify functioning of the
process alarm safety interlocks. Setpoints for the safety interlocks are located in
Section 11, System Specific Information of this manual.
Item Task
Frequency
EFS2, Excess flow
Verify that process flow
rate above the setpoint
shuts the system down.
Every six months
PT2, Branch delivery
pressure
Verify that process
delivery pressure above
the setpoint shuts the
system down.
Every six months
PT1, Process inlet pressure
Verify that process inlet
pressure above the high-
high setpoint sounds the
alarm and shuts the
system down.
Every six months
Содержание GASGUARD TE10
Страница 2: ......
Страница 12: ...GASGUARD TE10 Distribution System Manual Air Products and Chemicals Inc Page i x...
Страница 70: ...GASGUARD TE10 Distribution System Manual Air Products and Chemicals Inc Page 3 4...
Страница 87: ...Section 4 Electrical Connections Revision August 2005 Page 4 7 Figure 4 5 Conduit and Conduit Seals...
Страница 92: ...GASGUARD TE10 Distribution System Manual Air Products and Chemicals Inc Page 4 12...
Страница 94: ......
Страница 154: ......
Страница 166: ......
Страница 174: ......
Страница 180: ......
Страница 188: ......
Страница 189: ...Appendix B Revision November 2004 Page B 1 Appendix B This Appendix contains the Nitrogen N2 Material Safety Data Sheet...
Страница 190: ...GASGUARD TE10 Distribution System Manual Air Products and Chemicals Inc Page B 2...
Страница 191: ...Appendix B Revision November 2004 Page B 3...
Страница 192: ...GASGUARD TE10 Distribution System Manual Air Products and Chemicals Inc Page B 4...
Страница 193: ...Appendix B Revision November 2004 Page B 5...
Страница 194: ...GASGUARD TE10 Distribution System Manual Air Products and Chemicals Inc Page B 6...