Installation & Commissioning Guide PKY470-700 Tri-Capacity Package with CM100 Control
Doc. No.0525-032
Ver. 9 180921
ELECTRICAL
DEMAND RESPONSE MANAGEMENT
DEMAND
MANAGEMENT
MODE
DESCRIPTION OF MODE
OPERATING MODE
DRM1
Compressor Off
Compressors ONLY will cycle OFF & remain off
for the entire Demand Response Event.
DRM2
Maximum 50% power use mode.
(Over each 1/2 hour period)
Compressor 1 operation only for the total
Demand Response event.
DRM3
Maximum 75% power use mode.
(Over each 1/2 hour period)
Compressor 2 operation only for the total
Demand Response event.
Refer to diagram below for
details of DRM connections.
1. Thread & Route the DRM input cables into the Unit
• Thread & Route cables as per previous wiring installation procedures.
2. Connect cables into the terminals
• Connect cables as shown above and as per wiring diagram provided with the unit.
TERMINALS
Secure the cables firmly
using the cable ties and
clamp provided in the
panels.
To Outdoor
Controller
7 8 9 11
DRM
Control Inputs
J7
DEMAND RESPONSE MANAGEMENT CONNECTION DIAGRAM
DEMAND RESPONSE
ENABLING DEVICE (DRED)
AS4755 COMPLIANT DEVICE
(OPTIONAL)
TERMINALS
OUTDOOR
CONTROLLER
11
COMMON (GND)
10
REMOTE ON/OFF
9
DRM 3
8
DRM 2
7
DRM 1
DRM 3
DRM 2
DRM 1
DI1
DI2
D32
D41
GND