EGCP-2 Engine Generator Control Package
Manual 26174
104
Woodward
Modbus ID
Sets the Modbus RTU network ID of the Unit. Units will be Modbus slaves.
Modbus Timeout
Sets the timeout time for Modbus communications. See the
Communications Manual 26181 for details.
Modbus Reset
Can be used to zero the Modbus error counts for the unit.
Calibration Menu
While each unit will be factory calibrated at Woodward prior to shipment, there
are bound to be some inputs/outputs affected by external wiring and/or interfaces
(relays, transformers, etc.) that will require calibration at the site during
commissioning.
The Calibration Menu allows calibration of all the analog inputs to the EGCP-2,
as well as the speed bias and voltage bias outputs.
All calibration points in the EGCP-2 are used to make the actual value of an
input, such as generator voltage, read out on the respective display screen of the
EGCP-2 the proper value of the signal being monitored.
In order to assist in calibrating the unit, each calibration menu item has the
sensed input being calibrated displayed on the lower two lines of the right hand
LCD screen. These values are updated every 200 milliseconds. All adjustments
in the configuration menus are immediate in their action (that is, values do not
need to be entered into memory to have an effect on the sensed input, or control
operation).
Example
: 380 Vac measured line to line on the generator A-B phase should read
380 Vac in the line to line voltage measurement area of the EGCP-2 “generator
status” menu. The EGCP-2 is configured for Line to Line voltage input.
The calibration menu item “PT Phase A Scale” will display the A-B generator
phase voltage in the lower two lines of the display. This value will change as the
PT Phase A Scale value is adjusted.