Stopping
Procedure
Perform the procedure below to stop the machine.
1. Turn the control switch
(c)
to the OFF (0) position.
Stopping
sequence
The following sequence of events will occur.
1. The burner will shut down.
2. The blower will stop when the machine is sufficiently cool.
Restarting
Perform the procedure below to restart the machine.
1. Turn the control switch
(c)
to the either position 1, position 2, or position 3.
Note: The green start button does not need to be pressed to restart the machine if
electric power is still connected to it.
2. Use the machine as normal.
Complete
shutdown
Perform the procedure below to shut down the machine.
For machines without gensets (i.e., shore-powered machines):
1. Stop the machine as stated above.
2. Disconnect the power supplies when the blower stops.
3. Disconnect and pack up the air ducts.
For machines with gensets:
1. Set the genset circuit breaker to the OFF position when the blower stops.
2. Allow the genset engine to run for approximately 5 minutes with no load.
3. Turn the genset key switch to the OFF position.
4. Disconnect and pack up the air ducts.
WARNING
Electric shock hazard. Electric power is still active at the blower and at the control
switch even when the machine is turned OFF.
►
Disconnect all electric power from the machine before servicing it.
wc_gr007193
c
Summary of Contents for HI750 Series
Page 6: ...ghi_tx001257gb_FM10 fm 6 Foreword HI750 ...
Page 27: ...HI750 Labels ghi_si000380gb_FM10 fm 27 BB CC FF ...
Page 115: ...wc_tx003699gb_FM10 fm 115 Kubota Genset Genset Maintenance ...
Page 122: ...ghi_td000360gb_FM10 fm 122 Technical Data HI750 Notes ...
Page 142: ......
Page 143: ......