Power On and Operational Test
Before connecting the G1K Power Adapter to AC power:
Verify that input voltage and Adapter input voltage are correct before you power up the system.
Recheck the cabling for incorrect connections, loose wires and wiring fragments that may cause
short-circuits.
Plug the power adapter cord into a power outlet.
Verify the system boots properly by checking the display of a telephone set.
You may now connect the battery back up unit if applicable.
Operational Tests
Check each telephone and CO line to verify that outgoing lines are connected properly.
Check that intercom calls can be made from extension to extension.
WARNING:
DISCONNECT THE POWER SUPPLY FROM THE AC POWER SOURCE BEFORE WIRING OR
CHANGING ANY WIRING.
Connect the Battery Backup
AFTER
AC power has been connected to the Power Supply.
Disconnect Battery Backup
BEFORE
disconnecting AC power from the Power Supply.
NOTICE:
ONCE THE SYSTEM OPERATES PROPERLY, PROCEED TO SYSTEM PROGRAMMING.
(REFER TO THE SYSTEM PROGRAMMING MANUAL.)
Special Immunity Protection for System and terminals
Adding
Noise Filters
to the points below can enhance the immunity capability of the system from outside
environmental noise.
For Line:
Summary of Contents for Lynx DK6 Series
Page 1: ...Telephone System Master Programming Manual Rev 2 1c ...
Page 2: ......
Page 24: ...Page 24 ...
Page 34: ...Page34 ...
Page 40: ...Page40 ...
Page 44: ...Page44 DK6 Key Telephone Key Layout 18 Button DK7 Key Telephone Key Layout ...