Installation
© Solarbayer GmbH [210205]
35
the position of the house (due to hillside
position or different building heights, drop
winds or dynamic pressure zones arise)
Position of the chimney on the roof (chimney
opening must be at least 0.5 m above the
highest point of roofs with an angle of
inclination of more than 20° or at least 1.0 m
away from roof surfaces with an angle of angle
of 20° or less)
Design of the chimney opening (decorative
attachments
create
bottlenecks
and
turbulence
which
prevent
undisturbed
introduction of the exhaust gases into the wind
flow)
In practice, it may happen that a chimney builds up
too high a delivery pressure continuously or
sometimes (due to changes in the weather, gusty
wind etc.). By installing a draft regulator, the burn-
up conditions can be kept almost constant, which
improves the efficiency. However, it is always
better to consult the responsible chimney specialist
at the planning stage!
Attention:
The whole chimney system must be installed in
accordance with the valid EN 13384 standard.
Incorrectly dimensioned chimney systems can lead
to malfunctions (dangerous situations).
A
effective chimney height
B
chimney draft controller with explosion flap
C
cleaning opening
D
exhaused pipe rising and insulated
E
total chimney height
allowable delivery pressure (previously referred to
as drawbar requirement) 2 mm WS = 0.2 mbar
Effective chimney height = height difference
between the exhaust gas inlet into the chimney and
the chimney outlet (according to EN 13384).
This calculation of the whole chimney system must
be made by the chimney supplier or an authorised
company.
Type
Max.
allowed
delivery
pressure
in mbar
Examples of suitable
chimneys
Diameter
Delivery
head
Design
type
BioX
15
0,20
140,
160
min. 7m
I
BioX
20
0,20
140,
160
min. 7m
I
BioX
25
0,20
140,
160
min. 7m
I
BioX
35
0,20
140,
160
min. 7m
I
BioX
45
0,20
160,
180
min. 7m
I