Safety notes
© Solarbayer GmbH [210205]
5
1
SAFETY NOTES
Please read the documentation carefully prior to commissioning and pay particular attention to the marked
safety notes. Please look up in these instructions anything about which you are unsure.
Ensure that you understand the instructions in this manual and that you are sufficiently informed about
the functioning of the biomass furnace system. Solarbayer is at your disposal at all times for any
questions.
For safety reasons the operator must not alter the system, the construction or its condition, without the
agreement of the manufacturer or their authorised representative.
Ensure you have sufficient fresh air entering the boiler room. (Please take note of any regional regulations
or directives).
The tightness of all connecting points is to be monitored before the system is started up.
A portable fire extinguisher of the prescribed size must be placed in front of the boiler room. (Please take
note of any regional regulations or directives).
When opening the combustion chamber doors take care that no flue gas and sparks are released. Never
leave the combustion chamber door open. Toxic gases may be emitted.
Never heat up the boiler with liquid fuels such as petrol or similar.
Carry out maintenance work (maintenance plan) regularly or make use of our customer services.
When maintaining the system or opening the control system the power supply must be interrupted and
the general valid safety regulations respected.
No fuels should be stored outside the equipment in the boiler room Furthermore, the storage of items not
required for operating the equipment is not permitted in the boiler room.
Always use low voltage lamps for lighting the storeroom (these must be approved for use by each
manufacturer).
The equipment can only be operated using designated fuels.
Prior to further transportation of ashes, these must be cooled down for a minimum period of 96 hours
before storage.
If you have any questions, please contact us on telephone no. +49 (0) 8421 / 93598-0
The first start-up must be carried out by Solarbayer factory customer service or an authorised specialist.
(otherwise guarantee claims are invalid)
The boiler conform the regulation of the Swiss VKF and respectively the particular state regulations
regarding fire prevention. The costumer is fully responsible for the compliance with those regulations.