Date Code 20011009
SEL-701-1 Monitor
Commissioning
Monitor Commissioning Procedure
6.3
Step 4.
Connect the PC to the monitor using the appropriate serial cable (SEL
Cable C234A or a null-modem cable). Start the PC and terminal
emulation software. Establish communication with the monitor at
Access Level 1. Refer to
Section 5: ASCII Serial Port Operation
for
more information on serial port communications. Enter Access
Level 2 using the factory default password, 701.
HINT:
Use the HELP command at any Access Level to get a list
of available serial port commands.
Step 5.
Using the front-panel Set Monitor\Date and Set Monitor\Time
functions or serial port
DATE
and
TIME
commands, set the correct
monitor clock time and, if necessary, date.
Step 6.
Using the front-panel Set Monitor\Password or serial port Access
Level 2
PASSWORD
command, enter your new Access Level 2
password. Be sure to record the new password in a safe location.
Step 7.
Using the
SET
,
SET R
, and
SET P
commands, enter monitor settings
according to the Settings Sheets for your application.
Step 8.
If you are using an SEL-2600 RTD Module, connect the fiber-optic
cable to the module fiber-optic output. At the monitor-end of the
fiber, you should be able to see a red light that indicates the module is
sending data. Plug the monitor-end of the fiber into the monitor fiber-
optic receiver input.
Step 9.
Verify monitor ac connections. Connect the protective monitor ac test
signal source to the SEL-701-1 Monitor through the motor control
center wiring. (You may connect directly to the monitor; however,
this does not verify the accuracy of the wiring in the motor control
center.) Apply rated ac current (1 A or 5 A) to the monitor phase
current inputs. If the monitor is equipped with voltage inputs, apply
rated voltage for your application to the monitor phase voltage inputs.
If you set the monitor to accept phase-to-neutral voltages
(DELTA_Y = Y), set the current and/or voltage source phase
angles as shown in
.
If you use open-delta potentials, set the test source phase angles
as shown in
.
When you set the monitor to accept single-phase voltage
(SINGLEV = Y), you can connect and apply VA or VAB only.
Use the front-panel Meter Values\Instantaneous Meter function
or serial port
METER
command to verify that the monitor is
measuring the magnitude and phase angle of both voltage and
current correctly, taking into account the monitor PTR and CTR
settings and the fact that the quantities are displayed in primary
units. This step verifies the signal polarity and per-phase ac
connections to the monitor.
Summary of Contents for SEL-701-1
Page 16: ...This page intentionally left blank ...
Page 18: ...This page intentionally left blank ...
Page 20: ...This page intentionally left blank ...
Page 34: ...This page intentionally left blank ...
Page 118: ...This page intentionally left blank ...
Page 142: ...This page intentionally left blank ...
Page 196: ...This page intentionally left blank ...
Page 210: ...This page intentionally left blank ...
Page 242: ...This page intentionally left blank ...
Page 384: ...This page intentionally left blank ...