INSTALLATION
Installation Instructions for SIS Bus Bar Systems A2MS001EN revision R05
94 / 130
7.
Check the bolt connections for earthing to make
sure they are firmly locked, and mark them with a red
paint pen to indicate they have been tightened with
torque.
Individual Earthing
………………………. Personnel:
Installation Staff
Protective Equipment:
Occupational Safety Clothing
Protective Gloves
Safety Footwear
The earthing is stipulated in the earthing diagram. The
drawings in the documentation folder show a basic
illustration of the earthing options.
…
Earth each part individually with the material
included with the delivery. The rest of the earthing
process is as described under ‘Parallel Earthing’ within
this chapter.
4.10
FINAL INSPECTION
4.10.1
VISUAL INSPECTION AND
FILLING OUT THE CHECK
LISTS
Personnel:
Installation Staff
Protective Equipment:
Safety Goggles
Protective Gloves
Safety Footwear
1.
Once installation of the entire bus bar system has been
completed, perform a visual inspection. In the process,
the following is particularly important:
Damage to the bus bar surface?
All earthing connections are correct (individual
earthing
or parallel earthing)
Torque marking
Checking the bus bar system against the check list
Attach rating plates where they are visible!
2.
Fill out all check lists which are the check list for
inspecting one bus bar system for each system (see
Appendix F on page 115), the check lists for each
transport box (see Appendix G on page 124), the check
lists for each indoor connection sleeve (see Appendix H
on page 129) and the check lists for each outdoor
connection sleeve (see Appendix I on page 130).