INSTALLATION
Installation Instructions for SIS Bus Bar Systems A2MS001EN revision R05
48 / 130
Required tools and components
………
Fig. 19: Overview of the individual parts
The following tools are required for installation:
Hot air gun
Cable stripper
Side cutter
Crimping tool for cable lugs
The following components are required:
Earthing cable
Cable lug
Shrinking sleeve for earthing cable
Preparing one earthing cable
………..
Personnel:
Installation staff
Protective Equipment:
Occupational safety clothing
Protective gloves
Safety footwear
1.
Cut the earthing cable to the desired length using
the side cutter.
Fig. 20: Stripping the cable at one end
2.
Strip the cable at one end of the cable using the
cable stripper (see Fig. 20).
Fig. 21: Aligning the stripped cable and the
cable lug
3.
Put the stripped cable into the cable lug. Make
sure to use the full length of the cable lug and that the
distance between the insulation of the cable and the
cable lug is 3 mm +/- 1 mm (see Fig. 21).