Values at part load for G20 (H gas)
O
2
(%)
CO
2
(%)
(1) Nominal value
Tab.24 Checking/setting values for O
2
/CO
2
at low load for
G30/G31 (butane/propane)
Values at low load for G30/G31 (bu
tane/propane)
O
2
(%)
CO
2
(%)
Quinta Ace 160
5.4
(1)
- 5.7
10.0 -
10.2
(1)
(1) Nominal value
Caution
The O
2
values at low load must be higher than the O
2
values at
full load.
The CO
2
values at low load must be lower than the CO
2
values
at full load.
4. If the measured value is outside of the values given in the table, cor
rect the gas/air ratio.
5. Using the adjusting screw B, set the percentage of O
2
/CO
2
for the
gas type being used to the nominal value. This should always be
within the maximum and the minimum setting limits.
7.4
Final instructions
1. Remove the measuring equipment.
2. Screw the cap on to the flue gas measuring point.
3. Put the front casing back. Tighten the two screws by a quarter of a
turn.
4. Heat the CH system up to approximately 70°C.
5. Switch the boiler off.
6. Vent the central heating system after approx. 10 minutes.
7. Turn on the boiler.
8. Check the water pressure. If necessary: top up the central heating
system.
9. Specify the gas type used on the type plate.
10. Instruct the user in the operation of the system, boiler and controller.
11. Inform the user of the maintenance to be performed.
12. Hand over all manuals to the user.
13. Confirm the commissioning with a signature and a company stamp.
The boiler is now ready for operation.
Important
The boiler is delivered with set values for the parameters. These
factory settings are set to suit the most common central heating
systems. The parameters can be changed for deviating systems
and situations.
See
Manual for the control panel.
Important
Complete the checklist.
7 Commissioning
7625116 - v.04 - 17012017
43