5. Enter appropriate values in the fields.
Bank monitor
Indicates which cooling bank is being initialized. This field is for
informational purposes only.
Cycle on time
Allows you to enter the number of minutes for the cooling system to
be on while the 509ITM is learning the system parameters.
Cycle off time
Allows you to enter the number of minutes for the cooling system to
be off while the 509ITM is learning the system parameters.
Test cycles
Allows you to enter the number of times for the cooling system to
cycle while the system is being evaluated. Qualitrol recommends a
minimum of 10 cycles to get a good system average.
6. Click [Initialize].
The cooling system begins to cycle. The relay controlling the fan/pump motor de-
energizes for the time entered in the
Cycle off time
field. When the time
expires, the
relay/cooling system toggles on and off until it reaches the number in the
Test Cycles
field. The approximate time to run the initialization cycle can be calculated by:
(((Cycle Time On + Cycle Time Off) * Test Cycles) + Cycle Time Off)
7. Wait for the initialization process to finish.
window again.
The average, maximum, and minimum values for the current are displayed.
9. Using the values from the initialization process, finish filling in the
Summary of Contents for 509ITM Series
Page 26: ...26 www qualitrolcorp com Current Input Wiring...
Page 55: ...55 www qualitrolcorp com 3 Continue with the setup procedure...
Page 101: ...101 www qualitrolcorp com...
Page 144: ...144 www qualitrolcorp com The following window will appear...
Page 167: ...167 www qualitrolcorp com The Customer Setup window displays 4 Click Load Tap Changer...
Page 178: ...178 www qualitrolcorp com Appendix...
Page 179: ......
Page 180: ......
Page 181: ......