4.6 Transportation
Fig. 8: Transport equipment
1
1
2
For transporting the boiler to the installation location using a crane, transport eyes
found on the top of the boiler (
Fig. 8
, Pos. 1
) can be used. Remove the centre cov-
ering lid of the EuroCondense three to do this.
For the transport of the boiler to installation location manually, push 2 sufficiently
large steel pipes (Ø = 1", not included!) through the carrying fixture (
Fig. 8
, Pos. 2
),
so that the boiler can be lifted and transported.
Danger of injury!
The boiler must absolutely be secured from sliding on the steel
pipes! For transport manually safety shoes must be worn! For transport with the
aid of a carrier fixture at least 4 persons are required.
Before installation
7308536-02 06.13
Condensing gas boiler Eurocondense three125-300 kW
23