9. Maintenance
9.1 Inspection and need
dependent service
Note:
It is recommended to carry out maintenance of the EuroCondense three annually.
Should during inspection the need for maintenance work be found, these should
be carried out according to need.
Maintenance work includes among others:
- Clean EuroCondense three outside.
- The burner has to be checked for contamination and, possibly, to be cleaned and
serviced.
- Clean burner areas and heating surfaces
- Replace wear parts (see
Spare parts list
)
Caution!
Only original spare parts must be used.
- Check connection and seal locations of water filled parts.
- Check safety valves for correct function.
- Check operating pressure and, possibly, fill in water.
- De-aerate heating plant
- De-aerate heating plant and return gravity lock into operating position.
- End control and documentation of performed service work
Tip: Conclude a maintenance contract!
In order to guarantee an optimum operation, recommend to have a service con-
tract.
Maintenance
128
Condensing gas boiler Eurocondense three125-300 kW
7308536-02 06.13