Fig. 31: Boiler view Eurocondense three 215-300
Ionisation electrode
Sight glass
Fan
Boiler control LMS
Ignition electrodes
Venturi tube
Gas valve
Heating return
Heating flow
Gas connection
Flue gas connection
Safety group connection
Supply air connection
Heat exchanger
Silencer
Ignition transformer
(below the control unit)
Syphon
Servicing cover
Pressure switch
(below the control unit)
9.3 Disassembling and installing
burner
Risk of electric shock!
Before performing service work, power to the boiler must be
shut off and it must be secured from accidentally being switched back on!
Disassembling burner
1. Close gas shut off device
2. Remove front panel of the SGB E gas condensing boiler
3. Release ignition cable, ionisation line and earthing cable.
Maintenance
130
Condensing gas boiler Eurocondense three125-300 kW
7308536-02 06.13