9-6
Performing tests using a DCSM
411-2051-500
Draft
00.01
November 1999
Measuring Forward Control Channel RF power
The DCSM can be directed to take a Power measurement on the currently
active CCH. Raw RSSI readings are returned from the DCSM and are
translated into dBm at the CM. Procedure 9-3 is used to test the forward
power.
Measuring Reverse Control Channel power
For this test the DCSM is directed to terminate a call. The MTX then directs
the CCH to measure the TX power of the DCSMs page response (RECC or
RACH). The readings are in a raw format and are translated into dBm at the
CM. Procedure 9-4 is used to test the reverse power.
Procedure 9-3
Measuring forward CCH RF power
Step
Action
Observation
1
Make sure that the DCCH and the DCSM have been posted and
are in the INSV state as per the Control Channel Test Setup
Procedure.
2
At the CCH LEVEL OF THE MAP, enter:
>
TST POWER
Procedure 9-4
Measuring reverse CCH RF power
Step
Action
Observation
1
Make sure that the DCCH and the DCSM have been posted and
are in the INSV state as per the Control Channel Test Setup
Procedure.
2
At the CCH LEVEL OF THE MAP, enter:
>
TST RSSI
Summary of Contents for DualMode 800
Page 2: ......
Page 4: ......
Page 6: ...vi Publication history Nortel Networks Confidential 411 2051 500 Draft 00 01 November 1999...
Page 82: ...2 20 Periodic maintenance 411 2051 500 Draft 00 01 November 1999...
Page 90: ...3 8 Test equipment and precautions 411 2051 500 Draft 00 01 November 1999...
Page 100: ...5 6 Master Oscillator tests 411 2051 500 Draft 00 01 November 1999...
Page 106: ...6 6 Antenna and transmission line tests 411 2051 500 Draft 00 01 November 1999...
Page 116: ...8 4 Alarm Control Unit ACU tests 411 2051 500 Draft 00 01 November 1999...
Page 138: ...10 2 ICRM tests 411 2051 500 Draft 00 01 November 1999...
Page 200: ...12 10 Enclosure maintenance 411 2051 500 Draft 00 01 November 1999...
Page 208: ...A 8 Appendix A Frequency table 411 2051 500 Draft 00 01 November 1999...
Page 215: ......