19
Controller Type
”
B
Ü
, see 6.4 (PCGEZ 37 to PCGEZ 180)
1)
Remove the front plate and the two side panels.
2)
Open the tank cap and fill the tank (using a T-fitting if necessary) while watching the level indicator (refer to Fig. 1, Point
5.2.1).
3)
Open the filler screw on the pump head.
4)
Tighten the screw again when only water-glycol mixture flows out.
5)
Open the shut-off valve.
6)
Open the switch cabinet with the key supplied (Fastened to the main switch when the chiller is delivered).
7)
Ensure that the motor protection switches (
”
MTC
’
and
”
MTP
’
) are in position
”
0
’
.
8)
Fill the tank to the maximum (upper arrow, level indicator is located on the bottom right of the frame). See Section 6.1.1
(Water requirements).
9)
Move the motor protection switches
”
MTC
’
and
”
MTP
’
to position
”
1
’
.
10)
Make sure that the water-glycol mixture is able to circulate adequately. It the circuit might be interrupted by something
such as a valve, electrical valve, a filter or anything else, a by-pass circuit (automatic overflow valve) must be installed in
order to prevent damage to the pump.
11)
Lock the switch cabinet with the key.
12)
Move the main switch of the chiller to position
”
1
’
(the temperature of the cooling medium is displayed).
Never touch any part of the cooling circuit when the chiller is running!
13)
Start up the compressor by pressing the
button for 3 seconds.
14)
Make sure that the direction of rotation for the pump matches the direction of the arrow on the casing because the pump
starts up immediately. If it is rotating in the opposite direction, turn off the main switch of the chiller immediately and ar-
range for the polarity to be reversed.
15)
After a few minutes carefully open the filler screw again in order to remove any residual air. Tighten the screw again af-
terwards.
16)
Wait until the chiller has attained the operating conditions. This is indicated when the actual temperature shown in the
display matches the preset target temperature.
17)
Check whether the pressure shown is within the limits specified for the pump. If not, take appropriate action to ensure
that pump is able to run within the specified limits.
18)
Check the level in the tank and top it up if required. Put the tank cap back in place.
19)
Wait for the compressor to switch on. The compressor symbol will appear on the display.
20)
Check the inside of the chiller and the piping system for leakage or loose connections.
21)
Fit the front panel and the two side panels back into place.
22)
The chiller is normally factory-set to the temperature required by the customer.
22)
When the chiller is within the operating conditions set by the manufacturer, check whether the current uptake of the
chiller matches the data indicated on the identification plate and those contained in the table in the supplement.
Controller Type
”
C
Ü
, see 6.4 (PCGEZ 240 to PCGEZ 480)
1)
Remove the front plate and the two side panels.
2)
Open the tank cap and fill the tank (using a T-fitting if necessary) while watching the level indicator (refer to Fig. 1, Point
5.2.1).
3)
Open the filler screw on the pump head.
4)
Tighten the screw again when only cooling medium flows out.
5)
Open the shut-off valve.
6)
Open the switch cabinet with the key supplied (Fastened to the main switch when the chiller is delivered).
7)
Ensure that the motor protection switches (
”
MTC
’
and
”
MTP
’
) are in position
”
0
’
.
8)
Fill the tank to the maximum (upper arrow, level indicator is located on the bottom right of the frame). See Section 6.1.1
(Water requirements).
9)
Move the motor protection switches
”
MTC
’
and
”
MTP
’
to position
”
1
’
.
10)
Make sure that the water is able to circulate adequately. It the circuit might be interrupted by something such as a valve,
electrical valve, a filter or anything else, a by-pass circuit (automatic overflow valve) must be installed in order to pre-
vent damage to the pump.
11)
Lock the switch cabinet with the key.
12)
Move the main switch of the chiller to position
”
1
’
(the temperature of the cooling medium appears on the display).
Never touch any part of the cooling circuit when the chiller is running!
13)
Start up the chiller by pressing the
button (LED lights up).
14)
Because the pump starts up immediately, make sure that the direction of rotation for the pump matches the direction of
the arrow on the casing. If it is rotating in the opposite direction, turn off the main switch of the chiller immediately and
arrange for the polarity of the chiller to be reversed.
15)
After a few minutes carefully open the filler screw again in order to remove any residual air. Tighten the screw again af-
terwards.
16)
Wait until the chiller has attained the operating conditions. This is indicated when the actual temperature shown in the
display matches the preset target temperature.
17)
Check whether the pressure shown is within the limits specified for the pump. If not, take appropriate action to ensure
that pump is running within the specified limits.
18)
Check the level in the tank and top up with cooling medium if required. Fasten the tank cap afterwards.
19)
Wait for the compressor to switch on. The compressor symbol will appear on the display (see Section 6.4).
20)
Check the inside of the chiller and the piping system for leakage or loose connections.
21)
Fit the front panel and the two side panels back onto the casing.
22)
Check the preset target value. The chiller is normally factory-set to the temperature required by the customer.
23)
When the chiller is within the operating conditions set by the manufacturer, check whether the current uptake of the
chiller agrees with the data indicated on the identification plate and with those contained in the table in the supplement.
Summary of Contents for OCGE 111
Page 69: ...69 11 2 WIRING DIAGRAM MODELS PCGE 11 to PCGE 25 PCGEZ 08 230V 1Ph 50Hz POWER COMMAND DIAGRAM ...
Page 70: ...70 MODEL PCGE 28 230V 1Ph 50Hz POWER COMMAND DIAGRAM ...
Page 71: ...71 MODEL PCGE 28 400V 3Ph 50Hz POWER COMMAND DIAGRAM ...
Page 72: ...72 MODELS PCGE 31 to PCGE 41 OCGE 31 to OCGE 41 230V 1Ph 50Hz POWER SECTION ...
Page 73: ...73 MODELS PCGE 31 to PCGE 41 OCGE 31 to OCGE 41 230V 1Ph 50Hz COMMAND SECTION ...
Page 78: ...78 MODELS PCGE 590 to PCGE 3300 PCGEZ 360 to PCGEZ 480 400V 3Ph 50Hz ...
Page 79: ...79 ...
Page 80: ...80 ...
Page 81: ...81 ...
Page 86: ...86 MODEL PCGE 1100 with tank and pump MODEL PCGE 1300 with tank and pump ...
Page 87: ...87 MODEL PCGE 1900 2200 with tank and pump MODEL PCGE 2900 3300 with tank and pump ...
Page 91: ...91 MODEL PCGE 1100 without tank MODEL PCGE 1300 without tank ...
Page 92: ...92 MODEL PCGE 1900 2200 without tank MODEL PCGE 2900 3300 without tank ...
Page 97: ...97 710 1789 00 00 02B 轜 07 05 2008 ...
Page 166: ...69 11 2 WIRING DIAGRAM MODELS PCGE 11 to PCGE 25 PCGEZ 08 230V 1Ph 50Hz POWER COMMAND DIAGRAM ...
Page 167: ...70 MODEL PCGE 28 230V 1Ph 50Hz POWER COMMAND DIAGRAM ...
Page 168: ...71 MODEL PCGE 28 400V 3Ph 50Hz POWER COMMAND DIAGRAM ...
Page 169: ...72 MODELS PCGE 31 to PCGE 41 OCGE 31 to OCGE 41 230V 1Ph 50Hz POWER SECTION ...
Page 170: ...73 MODELS PCGE 31 to PCGE 41 OCGE 31 to OCGE 41 230V 1Ph 50Hz COMMAND SECTION ...
Page 175: ...78 MODELS PCGE 590 to PCGE 3300 PCGEZ 360 to PCGEZ 480 400V 3Ph 50Hz ...
Page 176: ...79 ...
Page 177: ...80 ...
Page 178: ...81 ...
Page 183: ...86 MODEL PCGE 1100 with tank and pump MODEL PCGE 1300 with tank and pump ...
Page 184: ...87 MODEL PCGE 1900 2200 with tank and pump MODEL PCGE 2900 3300 with tank and pump ...
Page 188: ...91 MODEL PCGE 1100 without tank MODEL PCGE 1300 without tank ...
Page 189: ...92 MODEL PCGE 1900 2200 without tank MODEL PCGE 2900 3300 without tank ...