TURBOCAR
Installation
4
0.0 11/22
INST
AL
L
AT
IO
N
5.5 ASSEMBLY OF THE TROLLEY LOADER AND VERTICAL EXTENSIONS:
For most cases, the trolley loader and the vertical extensions are already assembled and
are tied to the machine with wire, therefore:
1) cut the blocking wire (see arrow fig. 4.5.24);
2) lower the trolley loader (Z) and the extensions (AA) with forklift truck or crane (see
paragraph 4.3);
3) extract the extensions and fix them with the relevant pin and cotter to the spade
(U) (fig. 4.5.25);
(fig. 4.5.24) (fig. 4.5.25)
If the machine is delivered with trolley loader and extensions disassembled:
1) use a forklift truck or crane (see paragraph 4.3) to lift the trolley loader (BA) and fix
it with screws and self-locking nuts on the two attachments (CA) welded on the
frame (fig. 4.5.26);
2) while keeping the trolley loader on the forklift truck or crane, extract the extensions
(AA) and fix them with the appropriate pin and cotter to the spade (U) (fig. 4.5.25);
(fig. 4.5.26)
5.6 ASSEMBLY OF THE WATER SYSTEM
For transport reasons (rarely) the water system is disassembled; if the water system is
disassembled, each component must be lifted and use slings and a forklift truck, crane or
hoist to assemble, fixing each component with screws and nuts.
The photos below show two systems of the machines that in certain cases are
disassembled (fig. 4.5.27 – 4.5.28).
WHEN ASSEMBLING THE SYSTEM PAY ATTENTION TO FITTING THE SEAL AND
NOT TO DAMAGE THE GASKETS.
(fig. 4.5.27) (fig. 4.5.28)