From the front of the rack, line up the two pins on the rear of the slide rail in the selected U on the
rear of the rack. Push the rails so that the pins go into the holes and slide the rails into the rack to
lock the rear of the slide rails into the rack.
4.
Prepare the front end of the slide rails, as shown in Figure 50.
Push the blue button to allow the latch to slide forward. Then pull the slide rail forward and pull the
latch on the front of the rail in the U on the front of the rack. Adjust the length of the rail.
5.
Install the front end of the slide rails, as shown in Figure 51 on page 69.
Rear of rack
Figure 49. Installing the rear end of the slide rails
Figure 50. Preparing the front end of the slide rails
68
IBM SAN Volume Controller Hardware Maintenance Guide
Summary of Contents for SAN Volume Controller 2145-CG8
Page 1: ...System Storage SAN Volume Controller Hardware Maintenance Guide Version 6 2 0 GC27 2283 00...
Page 2: ......
Page 3: ...System Storage SAN Volume Controller Hardware Maintenance Guide Version 6 2 0 GC27 2283 00...
Page 14: ...xii IBM SAN Volume Controller Hardware Maintenance Guide...
Page 24: ...xxii IBM SAN Volume Controller Hardware Maintenance Guide...
Page 30: ...xxviii IBM SAN Volume Controller Hardware Maintenance Guide...
Page 54: ...24 IBM SAN Volume Controller Hardware Maintenance Guide...
Page 362: ...332 IBM SAN Volume Controller Hardware Maintenance Guide...
Page 364: ...334 IBM SAN Volume Controller Hardware Maintenance Guide...
Page 371: ......
Page 372: ...Part Number 31P1584 Printed in USA GC27 2283 00 1P P N 31P1584...