NetCol5000-A020 Air Cooled In-row Precision Air
Conditioner
User Manual
4 Power-On Commissioning
Issue 01 (2014-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
60
4
Power-On Commissioning
4.1 Tools
Tools for commissioning the NetCol5000-A020 are as follows:
Wrench: adjustable wrench.
Vacuumization and charging tools: pressure gauge (scale > 4.0 MPa), pipe (bearing
pressure > 4.0 MPa), and vacuum pump.
Measuring tools: multimeter, clamp meter, and electronic balance.
Protective tools: insulation gloves, boots, and antifreeze gloves.
Others: torch.
4.2 Partially Charging in Refrigerant
4.2.1 Calculation Requirements of Chilled Oil and Refrigerant to
Be Charged
Partially Charging in Refrigerant
If the length of one-way liquid pipeline is 7.5 m or shorter,
Table 4-1
shows the amount of
refrigerant to be charged according to the different outdoor unit. The actual amount of
refrigerant based on the commissioning onsite.
Table 4-1
Refrigerant configuration principle 1
Class
NetCol500-A0384C11E0
NetCol500-A0324C11E0
–5°C to +52°C
–15°C to +45°C
Basic refrigerant
charge
7 kg
5.7 kg
If the liquid pipe is longer than 7.5 m, charge in extra refrigerant excluding the basic