(43) Fix the cable unit to the flange of the Joint #4
actuator unit with the cable ties.
Cable ties (AB200) × 2 (1 and 2)
Tightening strength: 85
±
5 N
1
2
A7
B7
Refer to the figure for positions of the cable
tie heads.
Rotate the heads of the cable ties A7 and B7
to set positions.
Distance between the cable tie 1 and A7, and 3 and B7 should be as close as possible.
(Do not pull the cables forcibly to get close the cable ties.)
Be careful not to bend the air tubes.
Improper order or position of the cable tie may shorten the life cycle of the cables.
(44) Place marks on the cable of cable A (near the
cable ties A7 and A8) on the opposite side of
the flange.
(45) As with the above, place marks on the cable
or the air tube of cable B (near the cable ties
B7 and B8) on the opposite side of the
flange.
(46) Install the cable fixing plates to the flange of
the Arm #4.
Hexagon socket head cap bolts: 2-M4×8
Tightening torque: 4.0
±
0.2 N·m
NOTE
Summary of Contents for N6 Series
Page 1: ...Rev 2 EM187R3735F 6 Axis Robots N6 series MANIPULATOR MANUAL ...
Page 2: ...Manipulator manual N6 series Rev 2 ...
Page 8: ...vi N6 Rev 2 ...
Page 14: ......
Page 27: ...Setup Operation 1 Safety N6 Rev 2 15 N6 A850 R C A D F G F E H G F B G F G F F F N6 A850 BR F ...
Page 34: ...Setup Operation 2 Specifications 22 N6 Rev 2 N6 A850 BR Cable direction Upward ...
Page 52: ...Setup Operation 3 Environment and Installation 40 N6 Rev 2 N6 A850 R Maximum motion range 802 ...
Page 66: ...Setup Operation 4 End Effectors 54 N6 Rev 2 N6 A850 R Unit mm ...
Page 104: ......
Page 274: ...Maintenance 4 Cable 262 N6 Rev 2 4 7 1 Signal Power cable ...
Page 275: ...Maintenance 4 Cable N6 Rev 2 263 ...
Page 276: ...Maintenance 4 Cable 264 N6 Rev 2 4 7 2 User Cable ...