6 Commissioning
Hauser
23
6
Commissioning
6.1
Function check
#
Warning!
Before power-up, make sure there is no danger to the measuring point. Uncontrolled
actuated pumps, valves or similar could lead to damage to instruments.
"
Caution!
•
Before switching on, check all the connections again for correctness.
•
Make sure that the conductivity sensor and, if necessary, the temperature sensor are
in the medium or in a calibration solution, as otherwise no plausible measured value
can be displayed.
•
Make sure also that the post-connection check has been carried out (s. chap. 4.3).
6.2
Switching on the measuring device
Before first start-up, make sure you understand how to operate the transmitter. You
should make particular reference to chapters 1 (Safety instructions) and 5 (Operation).
First commissioning
On first switch-on, the instrument starts automatically with the Quick Setup menu. This
asks you about the most important instrument settings. After you close the menu, the
instrument is ready for use and measurement in its standard configuration.
!
Note!
•
You must completely run through the Quick Setup menu. If you do not, the instrument
will not be operational. If you interrupt Quick Setup, it will start again the next time you
start it up until
all
the items have been processed and completed.
•
For parameter setting, you have to enter the specialist code (default setting 0000).