5.4
Gas supply
The operator is responsible for the gas supply and the corresponding connections and
pressure reducers.
The connection hoses with outer diameter (AD) 6 mm and inner diameter (ID) 4 mm
are provided with the device. Their lengths are 2 m. If other lengths are preferred,
please contact the Analytik Jena AG customer service department. The required gases
and their qualities are listed in the technical data (→ "Technical data for the
multi EA 5100 "
172).
5.5
Device layout and space requirements
The space required for the modular analysis system depends on all the components that
make up the measuring station. The analysis station always includes:
¡
Basic module
¡
1 sampling module (to the right of the basic device or on top of it)
¡
1 detection module (to the left of the basic device)
Several modules may also be placed in a row.
Component
Width x Height x Depth
[mm]
Mass [kg]
Arrangement
Basic module
multi EA 5100
510 x 470 x 550 mm
25 kg
Detection modules
N module 5100
300 x 500 x 550 mm
13 kg
As last detector in a
row
S module 5100 basic
S module 5100 MPO
300 x 470 x 550 mm
13 kg
Left/right of other
detectors
Cl module 5100
300 x 470 x 530 mm
12 kg
To the immediate left
of the basic module
S module 5100
coulometric
300 x 470 x 530 mm
11 kg
Left of the
Cl module 5100
C module 5100
300 x 470 x 530 mm
12 kg
Left/right of other
detectors
TOC module 5100
300 x 470 x 530 mm
12 kg
To the immediate left
of the basic module
or to the left of the
Cl module 5100
Sampling modules
ABD
520 x 210 x 500 mm
12 kg
To the right of the
basic module
MBD
500 x 80 x 80 mm
0.35 kg
To the right of the
basic module
MMS 5100
ca. 510 x 280 x 500 mm ca. 9.5 kg
On the basic module