Installation and commissioning
multi EA 5100
34
5.6
Installing and commissioning the analysis system
WARNING
Danger due to incorrect commissioning
¡
The analysis system may only be set up, mounted and installed by the
Analytik Jena AG customer service department.
¡
Any unauthorized access of the device can endanger the user and the operational
safety of the equipment and limits or completely voids any warranty claims.
NOTICE
Retain the transport packaging
Return transport for maintenance must be in the original packaging. This alone prevents
transport damage.
The basic module, the sampling modules and the detectors are unpacked and assembled
by the Analytik Jena AG customer service department or personnel trained and autho-
rized by them.
Check when unpacking the device for completeness and soundness of the delivery in ac-
cordance with the packing list included.
The customer service department tests the function of the analysis system after installa-
tion and documents the test.
Installing the basic module
}
Carefully remove the basic module and its components from the transport packaging.
Do not damage the transport packaging!
}
Place the basic module at its intended location.
}
Ensure adequate space for the additional system components (sampling modules,
detectors).
}
Install the combustion furnace (→ "Removing and installing the combustion furnace"
141).
}
Install the auto-protection valve assembly (→ "Maintenance of the auto-protection
valve assembly"
}
}
Place the additional system modules on their intended locations and connect them.
CAUTION
Danger of short circuit!
¡
Only connect the basic module and other system components when they are pow-
ered down and switched off.
¡
Before connecting the power supply cable, set the power switch of the rear of the
device to "0".
¡
Only use the IEC connection cable included in the scope of delivery for the connec-
tion to the power supply (VDE label, 1.5 m long). Extensions of the supply cable are
not permitted!