KOMET 200 - 600
WARNING! The controller needs to be disconnected while welding is
performed on the gate.
8.3
Installation at the gate and gate post
Drawing 7
1
Mounting support P
2
Mounting support P with base plate (on side)
1. Secure the mounting support P on the gatepost at a height above the
ground in which the mounting support T can also be secured properly on
the gate. Welding seams have to be matched to the metal sheet thickness
of the mounting support P.
2. Close the gate so that it presses against the end stopper. Determine the
connection point of the mounting support T at the gate. Make sure that the
distance to the gate is sufficient, so that the gate opener does not touch
the gate later during movement. Using a water level determine the correct
height. Keep the necessary distance “E“ between the mounting supports P
and T.
Drawing 8
1
Mounting support T
2
Mounting support T with base plate (on side)
3. For steel gates: connect the mounting support T to the gate using tack
welding. If neccessary weld the mounting support to a reinforcement plate
(on site) and connect the reinforcement plate to the gate using tack
welding. For other gates: weld the mounting support to a support plate (on
site, approx.120x80x15mm) and connect the support plate to the gate (e.g.
using screws).
18