Installation
40
4.1.4 LOAD SWITCHING AND GENERATOR VOLTAGE SENSING
PIN
No
DESCRIPTION
CABLE
SIZE
NOTES
39
Output relay C
1.0mm
AWG 18
Normally configured to control load switching device
(Recommend 10A fuse)
40
Output relay C
1.0mm
AWG 18
Normally configured to control load switching device
41
Output relay D
1.0mm
AWG 18
Normally configured to control load switching device
(Recommend 10A fuse)
42
Output relay D
1.0mm
AWG 18
Normally configured to control load switching device
V1
43
Generator L1 (U) voltage
monitoring
1.0mm²
AWG 18
Connect to generator L1 (U) output (AC)
(Recommend 2A fuse)
44
Generator L2 (V) voltage
monitoring input
1.0mm²
AWG 18
Connect to generator L2 (V) output (AC)
(Recommend 2A fuse)
45
Generator L3 (W) voltage
monitoring input
1.0mm²
AWG 18
Connect to generator L3 (W) output (AC)
(Recommend 2A fuse)
46
Generator Neutral (N) input
1.0mm²
AWG 18
Connect to generator Neutral terminal (AC)
NOTE: The above table describes connections to a three phase, four wire alternator. For
alternative wiring topologies, please see the ALTERNATIVE AC TOPOLOGIES section of this
manual.
4.1.5 BUS SENSING
These connections are to the common bus supply of the generator system.
PIN
No
DESCRIPTION
CABLE
SIZE
NOTES
V2
47
Bus L1 (R) voltage monitoring
1.0mm
AWG 18
Connect to Bus L1 (R) incoming supply (AC)
(Recommend 2A fuse)
48
Bus L2 (S) voltage monitoring
1.0mm
AWG 18
Connect to Bus L1 (S) incoming supply (AC)
(Recommend 2A fuse)
49
Bus L3 (T) voltage monitoring
1.0mm
AWG 18
Connect to Bus L1 (T) incoming supply (AC)
(Recommend 2A fuse)
50
Bus Neutral (N) input
1.0mm
AWG 18
Connect to Bus N incoming supply (AC)
Summary of Contents for DSE8610
Page 47: ...Installation 47 4 2 2 3 PHASE 4 WIRE WITHOUT EARTH FAULT PROTECTION...
Page 51: ...Installation 51 4 3 2 SINGLE PHASE WITHOUT EARTH FAULT...
Page 53: ...Installation 53 4 3 4 2 PHASE L1 L2 3 WIRE WITHOUT EARTH FAULT...
Page 55: ...Installation 55 4 3 6 2 PHASE L1 L3 3 WIRE WITHOUT EARTH FAULT MEASURING...
Page 118: ...Intentionally Left Blank 118...