64
999805802 - 03/2016
Start-up phases
Original Operating Instructions
Platform SCP
3rd casting section
➤
Start up the hydraulic unit.
➤
Lift the platform until the Vertical profiles
FRQ
120
and the Suspension profiles FRQ
50 can be fixed in
place.
➤
Fix the Vertical profiles FRQ
120 and the Suspen-
sion profiles FRQ
50 at the correct operational
height.
➤
Lift the platform to the next position (see the section
headed 'Typical sequence of lifting-phases').
➤
Lower base beam is pulled up.
Mounting suspended platforms in
shafts with base beams
➤
Set down the items needed for preparing the plat-
forms inside the shafts.
➤
Bolt a U100 profile to the Vertical profiles FRQ120/8.
Threaded-fastener material required
▪
2 hexagon bolts M20x160, strength grade 8.8
(EN ISO 4017 / DIN 933)
▪
2 washers 20 (EN ISO 7089)
▪
2 hexagon nuts M20, strength grade 8
(EN ISO 4032 / DIN 934)
➤
Pin the Multi-purpose waling WS10 Top50 to the
Suspension profiles FRQ
50 and secure with spring
cotters.
➤
Use beam screws to fix Doka beams onto the Multi-
purpose waling WS10 Top50 and the U100 profile.
➤
Fasten platform decking to the Doka beams with suf-
ficient numbers of universal countersunk screws
6x80.
A
Vertical profile FRQ 120 6.00m
B
U100 profile level -1 .....mm (project-specific)
C
Suspension profile FRQ
50
(project-specific)
D
Multi-purpose waling WS10
Top50
A
Vertical profile FRQ 120 6.00m
B
U100 profile level -1 .....mm (project-specific)
98058-405-07
A
C
B
D
98058-405-08
A
B
C
Suspension profile FRQ
50
(project-specific)
D
Multi-purpose waling WS10
Top50
E
Connecting pin 10cm
F
Spring cotter 5mm
G
Doka beam H20
H
Beam screw S 8/70
I
Platform decking
98058-405-09
C
D
E
F
G
H
98058-405-11
I
98058-405-06
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...