Start-up phases – Lifting unit attached on one side
Original Operating Instructions
Platform SCP
➤
Place floor props under the working platform.
Erecting the vertical scaffold
➤
Lift the pre-assembled vertical scaffold into the
Brackets SCP.
➤
Pin each Vertical profile 150 into the brackets with 4
Fastening bolts FRQ 150 and secure the bolts.
Included with the Vertical profile 150:
▪
4 Fastening bolts FRQ 150
▪
8 washers 21
▪
8 cotter pins 5x45
Positioning the formwork
➤
Prepare squared timbers for the correct operational
height along the entire length of the formwork.
➤
Attach the crane suspension tackle to the lifting
brackets on the pre-assembled formwork.
➤
Lift in the formwork elements and secure them
against tip-over.
➤
Mount temporary platforms (site-provided).
☞
Important note:
Overload of the temporary reshore
➤
Dimension the reshoring of the working plat-
form adequately.
The formwork will be set down on this working
platform at a later stage of the assembly pro-
cess.
H
Working platform
I
Floor prop
98058-461-05
H
I
98058-461-02
A
Bracket SCP
J
Vertical profile 150
K
Squared timber (height = project-specific)
L
Formwork element
98058-460-05
J
A
98058-461-04
K
L
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...