![Doka Platform SCP Original Operating Instructions / Instructions For Assembly And Use Download Page 48](http://html.mh-extra.com/html/doka/platform-scp/platform-scp_original-operating-instructions-instructions-for-assembly-and-use_2516579048.webp)
48
999805802 - 03/2016
Start-up phases
Original Operating Instructions
Platform SCP
Attaching pre-assembled grille-beam
pairs
➤
Mount temporary platforms (site-provided).
➤
Pass lifting slings around the grille-beam pair and
attach them to the lifting beam.
➤
Crane-lift the grille-beam pair to the vertical profiles.
Follow the directions in the 'Lifting beam 110kN
6.00m' Operating Instructions!
A
Temporary platform
B
Pre-assembled grille-beam pair
C
Lifting beam 110kN 6.00m
98058-422-11
A
A
A
B
C
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...