JT920/JT920L - OPERATION
REMOVE PIPE
110
JT920/JT920L - OPERATION
REMOVE PIPE
8.
Rotate pipe counterclockwise to unscrew bottom joint.
9.
Disengage breakout wrench to release pipe.
10. Rotate spindle counterclockwise and move carriage back
slightly to unscrew pipe from saver sub.
11. Move spindle away from pipe.
12. Load pipe into pipe box.
•
Ensure that pipe is aligned with pipe box.
•
Move loader shuttle under selected row in box and raise
lift arms to place pipe in box (JT920L only).
13. Attach next pipe to saver sub.
•
Use dual speed carriage control and move carriage
forward until saver sub touches pipe.
•
Rotate spindle and move carriage forward just enough to
allow pipe to screw into saver sub. Joint should only be
tight enough to prevent leaking.
14. Disengage front wrench to release pipe.
8.
Rotate pipe counterclockwise to unscrew bottom joint.
9.
Disengage breakout wrench to release pipe.
10. Rotate spindle counterclockwise and move carriage back
slightly to unscrew pipe from saver sub.
11. Move spindle away from pipe.
12. Load pipe into pipe box.
•
Ensure that pipe is aligned with pipe box.
•
Move loader shuttle under selected row in box and raise
lift arms to place pipe in box (JT920L only).
13. Attach next pipe to saver sub.
•
Use dual speed carriage control and move carriage
forward until saver sub touches pipe.
•
Rotate spindle and move carriage forward just enough to
allow pipe to screw into saver sub. Joint should only be
tight enough to prevent leaking.
14. Disengage front wrench to release pipe.
Summary of Contents for JT920
Page 54: ...54 JT920 JT920L SAFETY SAFETY ALERTS 54 JT920 JT920L SAFETY SAFETY ALERTS...
Page 68: ...68 JT920 JT920L PREPARATION 68 JT920 JT920L PREPARATION...
Page 75: ...JT920 JT920L TRANSPORTATION 75 TOW JT920 JT920L TRANSPORTATION 75 TOW...
Page 76: ...76 JT920 JT920L TRANSPORTATION TOW 76 JT920 JT920L TRANSPORTATION TOW...
Page 167: ......
Page 168: ......
Page 169: ...JT920 JT920L 169 JT920 JT920L 169...