The bore path, from entry to end, must be planned before drilling
begins. Bore path can be marked on ground with spray paint or
flags, or written on paper for operator reference.
For complicated bores, consult an engineer. Have jobsite
surveyed and bore path calculated. Be sure engineer knows
minimum entry pitch, bend limits of drill pipe and pullback
material, pipe lengths, and location of all underground utilities.
For less complicated paths, bore will be limited by four
measurements: recommended bend limits, entry pitch, minimum
setback, and minimum depth. Recommended bend limits must be
considered during any bend, not just during bore entry.
PLAN BORE PATH
The bore path, from entry to end, must be planned before drilling
begins. Bore path can be marked on ground with spray paint or
flags, or written on paper for operator reference.
For complicated bores, consult an engineer. Have jobsite
surveyed and bore path calculated. Be sure engineer knows
minimum entry pitch, bend limits of drill pipe and pullback
material, pipe lengths, and location of all underground utilities.
For less complicated paths, bore will be limited by four
measurements: recommended bend limits, entry pitch, minimum
setback, and minimum depth. Recommended bend limits must be
considered during any bend, not just during bore entry.
Summary of Contents for JT920
Page 54: ...54 JT920 JT920L SAFETY SAFETY ALERTS 54 JT920 JT920L SAFETY SAFETY ALERTS...
Page 68: ...68 JT920 JT920L PREPARATION 68 JT920 JT920L PREPARATION...
Page 75: ...JT920 JT920L TRANSPORTATION 75 TOW JT920 JT920L TRANSPORTATION 75 TOW...
Page 76: ...76 JT920 JT920L TRANSPORTATION TOW 76 JT920 JT920L TRANSPORTATION TOW...
Page 167: ......
Page 168: ......
Page 169: ...JT920 JT920L 169 JT920 JT920L 169...