Carry the unit by the slings, and put it onto the installation structure.
±150
kg
3
Remove the slings, and dispose of them.
4
Fix the unit to the installation structure.
6× M12
7.2.5 To provide drainage
▪
Make sure that condensation water can be evacuated properly.
▪
Install the unit on a base to make sure that there is proper drainage in order to
avoid ice accumulation.
▪
Prepare a water drainage channel around the foundation to drain waste water
away from the unit.
▪
Avoid drain water flowing over the footpath, so that it does NOT become slippery
in case of ambient freezing temperatures.
▪
If you install the unit on a frame, install a waterproof plate within 150 mm of the
bottom side of the unit in order to prevent water from getting into the unit and
to avoid drain water dripping (see the following figure).