Proprietary Information: Not for use or disclosure except by written agreement with Clearfield.
80
FieldSmart
®
Fiber Active Cabinet (FAC) 900
Installation Manual
_________________________________________________________
Step 4:
Step 5:
Step 6:
Step 7:
Step 8:
Step 9:
From inside the AC load center, push the plug out from the AC input hole and install the supplied cord grip and
locknut.
Pull the AC cable into the cabinet through the duct entry in the base of the cabinet.
Route the AC cable to the rear of the AC load center and feed it through the cord grip in the AC input hole.
Connect the AC wiring as follows:
•
Connect the green (ground) lead to the ground bus bar (strip and tin the wire as needed).
•
Connect the white (neutral) lead to the neutral bar.
• Connect the black L1 lead to the left side of the Main breaker.
• Connect the red L2 lead to the right side of the Main breaker.
Dress and secure the AC cable, providing adequate strain relief.
Replace the right cover panel on the AC load center.
AC Junction Box: Installing Power
Cabinets factory equipped with the AC junction box option support 120/240 VAC service in conjunction with use of 40 Amp
rectifier modules.
Note:
The AC junction box does not support 110/120 VAC input power.
DANGER!
High voltage may be present. Do not apply AC power to the cabinet until the installation process is
complete.
WARNING!
Electrical hazard. Only a qualified electrician should perform this procedure.
Before proceeding, verify that AC service to the cabinet site is OFF at the local power transfer switch.