Step 1:
Step 2:
Step 3:
Step 4:
Preparing the Cabinet for Installation
Complete the following preparations before installing the cabinet.
To prepare the cabinet for installation
Open the front and side cabinet doors.
From the side of the cabinet, remove the isolation mat and the bag containing the installation hardware. Set
them aside for use during installation.
In the front of the cabinet, remove the right AC cover panel as follows:
a.
Remove the (3) mounting screws securing the cover panel to the fixture.
b.
Push up on the (2) lifting tabs, angle the panel away from the fixture, and lift the panel from the (3) capture
tabs on the bottom of the fixture.
Remove the four bolts securing the cabinet to the pallet. The bolts are located at the bottom corners of the
cabinet, and can be accessed by removing the left and rear access panels as needed.
When the tasks above are complete, the cabinet is ready for installation.