Installation Manual
Direct: 763.476.6866 • National: 800.422.2537 • www.SeeClearfield.com • [email protected]
Manual 020420 REV B - April 2019
Step 8:
Step 9:
Step 10:
Connect the battery power supply leads as follows:
a.
Remove the protective caps from the cable ring lugs.
b.
Attach the black cable that is routed through the right upper
hole in the retaining bracket to the positive (+) terminal post at the
right end of the string.
c.
Attach the red cable that is routed through the left upper hole
in the retaining bracket to the negative (-) terminal post at the left
end of the string.
ALERT!
Use a volt meter to verify correct wiring polarities.
d.
Mount the temperature probe cable lug onto the string's negative (-) terminal post at the left end of the string.
e.
Tighten the hardware on the terminal posts to the torque specified by the manufacturer.
f.
If available, install protective covers (manufacturer-supplied) over the battery terminals.
Replace the retaining bracket and terminal cover.
Connect the Anderson power connectors together.
To connect a temperature probe cable to the cabinet power system (for VRLA batteries only)
WARNING!
Risk of electric shock. Only a qualified electrician should perform this task.
Note:
Two temperature probe cables are pre-wired to the rectifier, labeled
1
and
2
.
Step 1:
Step 2:
Step 3:
Mate the temperature probe cable from the primary battery string with the rectifier cable labeled
1
.
For a secondary battery string, route the rectifier cable labeled
2
to the battery enclosure, and then mate the
temperature probe cable with the rectifier cable.
Connect the terminal ring sensor end to the red (-) battery terminal.