Installing the Wall/H-Frame Mounting Fixture
This topic describes how to install the wall/H-frame mounting brackets and conduit feed through assembly.
To install the wall/H-frame mounting fixture
Attach the mounting brackets to the wall/H-frame horizontal beams as follows:
a.
Mark (4) pilot hole locations on the horizontal beams based on your selected configuration. See
Wall/H-
Frame Mounting Configurations and Drawings
for exact locations of pilot holes.
b.
Drill 3/8-inch pilot holes into the horizontal beams at the marked locations.
c.
Position the bracket against the wall/H-frame, as shown in the illustration below:
• Orient the bracket facing inward, with mounting slots against the wall/H-frame and on the top.
•
Align the top of the mounting bracket flush to the top edge of the middle horizontal beam, and center the
mounting slots on the drilled holes in the beam.
Note:
You can offset the horizontal position of the brackets later if needed, once the cabinet is roughly posi-
tioned.
d.
Install (1) 1/2"-13 x 3.00" hex screw, 1/2" split lock washer and 1/2" flat washer to attach the mounting brack
-
et to the front of the wall/H-frame.
e.
On the back side of the wall/H-frame, install (1) 1/2"-13 hex nut, 1/2" split lock washer and 1/2" flat washer.
f.
Verify that the bracket is level, and then tighten the hardware to secure the bracket in place.
g.
Repeat steps 1a–1f to install additional mounting brackets.
(For FAC 900 + EXM configurations only) Secure the two center mounting brackets together as follows:
a.
From the left side of the brackets, install (1) 1/2"-13 x 1.25" hex screw, 1/2" split lock washer and 1/2" flat
washer.
b.
On the right side of the brackets, install (1) 1/2”-13 hex nut, 1/2” split lock washer and 1/2” flat washer.
Step 1: