Voltmeter
Tools/Equipment
Applicable procedures in
Installing the ONS 15454 M6 Shelf, on page 1
Prerequisite Procedures
Required
Required/As Needed
Onsite
Onsite/Remote
None
Security Level
Procedure
Step 1
If you installed an ONS 15454 M6, complete the following table by verifying that each applicable procedure
was completed.
Table 9: ONS 15454 M6 Shelf —ETSI Rack Installation Task Summary
Completed
Description
NTP-G305 Unpack and Inspect the ONS 15454, ONS 15454 M2, and ONS 15454 M6 Shelves
NTP-G252 Install the ONS 15454 M6 Shelf , on page 24
Connect the chassis to the office ground. For detailed instructions on how to ground the chassis,
see the
Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms
NTP-G259 Open and Remove the Standard Door of the ONS 15454 M6 Shelf , on page 57
NTP-G253 Install the ECU or ECU-S Module, on page 79
NTP-G524 Install the Power Modules in the ONS 15454 M6 Shelf , on page 85
NTP-G255 Install the LCD Module in the ONS 15454 M6 Shelf, on page 96
NTP-G256 Install Power and Ground to the ONS 15454 M6 Shelf , on page 100
NTP-G257 Install the Fan-Tray Assembly in the ONS 15454 M6 Shelf, on page 118
NTP-G313 Install and Configure the TNC, TNCE, TSC, or TSCE Card
(as applicable)
NTP-G309 Connect the ONS 15454 M6 and the ONS 15454 in a Mixed Multishelf Configuration,
on page 139
(as applicable)
NTP-G310 Upgrade the ONS 15454 Multishelf Configuration Using the ONS 15454 M6 , on
page 149
(as applicable)
(as applicable)
NTP-G258 Install the Standard Door of the ONS 15454 M6 Shelf , on page 53
Installing the ONS 15454 M6 Shelf
156
Installing the ONS 15454 M6 Shelf
NTP-G264 Perform the ONS 15454 M6 Shelf Installation Acceptance Test