CHAPTER 5: SETUP SOFTWARE
UB25 LINEAR DC RESISTANCE WELDING CONTROL
5-18
990-665
The
DO TEST WELD
options are:
IF REQUIRED
The Power Supply will only do a Test Weld when the feedback mode is changed
to
voltage
or
power
as described above.
ASK
The Power Supply will do a Test Weld when the feedback mode is changed to
voltage
or
power
as described above. The Power Supply will also prompt the
operator if a Test Weld should be done (
TEST WELD? [MENU] = NO, [RUN]
= YES
) when
time
values
,
voltage
levels
, or
power levels
are changed on the
schedule.
ALWAYS
The Power Supply will do a Test Weld when the feedback mode is changed to
voltage
or
power
as described above. The Power Supply will also do a Test
Weld when
time
values
,
voltage
levels
, or
power levels
are changed on the
schedule.
1
From the
SETUP 3
menu screen, press
the
1
key to access the
DO TEST
WELD
screen.
2
Press the
1, 2, or 3
key to select the
desired option.
3
The display will automatically return to
the
SETUP 3
menu screen.
Ignore First/Last
1
From the
SETUP 3
menu screen, press
the
2
key to access the
IGNORE
FIRST/LAST
screen.
2
Use the numeric keypad to enter the time
in milliseconds that the Power Supply
ignores when calculating the load
resistance during the PID Test Weld.
The delay time prevents the Power
Supply from measuring noise early in the
test weld and allows for more accurate
load resistance to be measured.
3
Press
MENU
to return to the
SETUP 3
menu screen.
IGNORE FIRST/LAST
IGNORE FIRST/LAST
: 0.2ms
NUMBER Change, MENU Previous menu
DO TEST WELD
1. IF REQD
2. ASK
3. ALWAYS