Commissioning
P846/EN CM/D
MiCOM P846
(CM) 10-9
5.
PRODUCT CHECKS
These product checks cover all aspects of the relay which should be checked to ensure that
it has not been physically damaged prior to commissioning, is functioning correctly and all
input quantity measurements are within the stated tolerances.
If the application-specific settings have been applied to the relay prior to commissioning, it is
advisable to make a copy of the settings so as to allow their restoration later. This could be
done by:
•
Obtaining a setting file on a diskette from the customer (this requires a portable PC with
appropriate setting software for transferring the settings from the PC to the relay)
•
Extracting the settings from the relay itself (this again requires a portable PC with
appropriate setting software)
•
Manually creating a setting record. This could be done using a copy of the setting
record located at the end of this chapter to record the settings as the relay’s menu is
sequentially stepped through via the front panel user interface
If password protection is enabled and the customer has changed password 2 that prevents
unauthorized changes to some of the settings, either the revised password 2 should be
provided, or the customer should restore the original password prior to commencement of
testing.
Note:
In the event that the password has been lost, a recovery password
can be obtained from Alstom Grid by quoting the serial number of the
relay. The recovery password is unique to that relay and is unlikely to
work on any other relay.
5.1
With the relay de-energized
The following group of tests should be carried out without the auxiliary supply being applied
to the relay and with the trip circuit isolated.
The current and voltage transformer connections must be isolated from the relay for these
checks. If a P991 test block is provided, the required isolation can easily be achieved by
inserting test plug type P992 that effectively open-circuits all wiring routed through the test
block.
CM
Before inserting the test plug, reference should be made to the scheme (wiring) diagram to
ensure that this will not potentially cause damage or a safety hazard. For example, the test
block may be associated with protection current transformer circuits. It is essential that the
sockets in the test plug, which correspond to the current transformer secondary windings,
are linked before the test plug is inserted into the test block.
DANGER:
Never open circuit the secondary circuit of a current transformer since
the high voltage produced may be lethal and could damage insulation.
If a test block is not provided, the voltage transformer supply to the relay should be isolated
by means of the panel links or connecting blocks. The line current transformers should be
short-circuited and disconnected from the relay terminals. Where means of isolating the
auxiliary supply and trip circuit (e.g. isolation links, fuses, MCB, etc.) are provided, these
should be used. If this is not possible, the wiring to these circuits will have to be
disconnected and the exposed ends suitably terminated to prevent them from being a safety
hazard.
5.1.1
Visual inspection
The rating information given under the top access cover on the front of the relay
should be checked. Check that the relay being tested is correct for the protected
line/circuit. Ensure that the circuit reference and system details are entered onto the
setting record sheet. Double-check the CT secondary current rating, and be sure to
record the actual CT tap which is in use.
Summary of Contents for MiCOM P846
Page 2: ......
Page 4: ......
Page 5: ...Safety Section P846 EN SS H11 SS SAFETY SECTION...
Page 6: ...P846 EN SS H11 Safety Section SS...
Page 8: ...P846 EN SS H11 Safety Section SS 2 SS...
Page 16: ...P846 EN IT D Introduction MiCOM P846 IT...
Page 18: ...P846 EN IT D Introduction IT 1 2 MiCOM P846 IT...
Page 26: ...P846 EN TD D Technical Data MiCOM P846 TD...
Page 38: ...P846 EN GS D Getting Started MiCOM P846 GS...
Page 58: ...P846 EN ST D Getting Started MiCOM P846 ST...
Page 60: ...P846 EN ST D Settings ST 4 2 MiCOM P846 ST...
Page 78: ...P846 EN OP D Operation MiCOM P846 OP...
Page 104: ...P846 EN OP D Operation OP 5 26 MiCOM P846 OP...
Page 106: ...P846 EN AP D Application Notes MiCOM P846 AP...
Page 108: ...P846 EN AP D Application Notes AP 6 2 MiCOM P846 AP...
Page 122: ...P846 EN AP D Application Notes AP 6 16 MiCOM P846 AP...
Page 124: ...P846 EN PL D Programmable Logic MiCOM P846 PL...
Page 126: ...P846 EN PL D Programmable Logic PL 7 2 MiCOM P846 PL...
Page 144: ...P846 EN MR D Measurements and Recording MiCOM P846 MR...
Page 146: ...P846 EN MR D Measurements and Recording MR 8 2 MiCOM P846 MR...
Page 160: ...P846 EN FD D Firmware Design MiCOM P846 FD...
Page 182: ...P846 EN CM D Commissioning MiCOM P846 CM...
Page 228: ...P846 EN CM D Commissioning CM 10 46 MiCOM P846 CM...
Page 230: ...P846 EN MT D Maintenance MiCOM P846 MT...
Page 232: ...P846 EN MT D Maintenance MT 11 2 MiCOM P846 MT...
Page 238: ...P846 EN TS D Troubleshooting MiCOM P846 TS...
Page 240: ...P846 EN TS D Troubleshooting TS 12 2 MiCOM P846 TS...
Page 252: ...P846 EN SC D SCADA Communications MiCOM P846 SC...
Page 272: ...P846 EN SG D Symbols and Glossary MiCOM P846 SG...
Page 280: ...P846 EN SG D Symbols and Glossary SG 14 8 MiCOM P846 SG...
Page 282: ...P846 EN IN D Installation MiCOM P846 IN...
Page 284: ...P846 EN IN D Installation IN 15 2 MiCOM P846 IN...
Page 296: ...P846 EN IN D Installation IN 15 14 MiCOM P846 IN...
Page 297: ......