Commissioning Procedure
Motor S.F.:
_________________________________________________________
Motor L.R.A.:
______________________________________________________
Frequency:
________________________________________________________
Phases:
___________________________________________________________
Important Commissioning Checks
• Inspect the equipment for any signs of physical damage.
• Verify SMC-50 physical installation is complete.
• Verify the integrity and operation of all safety interlocks.
• Verify that motor mechanical installation is complete.
• Verify that Incoming Power wiring to SMC-50 is complete and all
connections are tight.
• Verify that Motor cabling to SMC-50 is complete and that all connections
are tight.
• Verify that Control wiring to SMC-50 is complete.
• Check for any damaged components and verify that electrical clearances
have not been reduced while installing power cables.
• Check if there are any Power Factor Correction Capacitors (refer to
Factor Correction Capacitors on page 62 of Chapter 2
for correct
installation requirements of these capacitors).
• Check if Surge Capacitors and/or Surge Arrestors are installed at the
motor. Open motor junction box and verify it by yourself. These must be
disconnected from the circuit. (refer to
Surge Arrestor Protection Devices
• Verify fiber-optic cables are connected at the right location (FO cables on
Phase-A power pole go to Phase-A on the Interface board, Phase-B of
power pole to Phase-B on the Interface board and Phase-C of power pole
to Phase-C on the interface board) and the connectors are fully seated in
their sockets.
ATTENTION:
When commissioning a SMC-50, it is critical that following
important checks are completed. For more details, follow the commissioning
guidelines that follow this page.
ATTENTION:
The polarity of the gate drive signals is important for proper
operation. For example, the A+ and A- transmitters from the interface board
must connect to the proper SCRs in the power electronics assembly. See
Summary of Contents for SMC-50
Page 10: ...10 Rockwell Automation Publication 1560F UM001A EN P June 2019 Table of Contents Notes ...
Page 12: ...12 Rockwell Automation Publication 1560F UM001A EN P June 2019 Preface Notes ...
Page 68: ...68 Rockwell Automation Publication 1560F UM001A EN P June 2019 Chapter 2 Installation Notes ...
Page 120: ...120 Rockwell Automation Publication 1560F UM001A EN P June 2019 Chapter 4 Programming Notes ...
Page 130: ...130 Rockwell Automation Publication 1560F UM001A EN P June 2019 Chapter 5 Metering Notes ...
Page 156: ...156 Rockwell Automation Publication 1560F UM001A EN P June 2019 Chapter 8 Diagnostics Notes ...
Page 198: ...198 Rockwell Automation Publication 1560F UM001A EN P June 2019 Chapter 10 Maintenance Notes ...
Page 284: ...284 Rockwell Automation Publication 1560F UM001A EN P June 2019 Appendix H Spare Parts Notes ...
Page 286: ...286 Rockwell Automation Publication 1560F UM001A EN P June 2019 Appendix I Accessories Notes ...
Page 291: ......