Printed Documentation
110
2. If required download the appropriate software by following the software download
procedure (see Software Download)
3. Re-boot the Shelf by clicking the Reset Shelf button on the shelf controller view.
Check Boot Sequence
1. SC card boots-up and displays the following LED sequence:
a. Red & green LEDs both ON
b. All LEDs OFF
c. Green LED FLASHING
d. Green LED ON
e. The red LED temporarily comes ON
2.
All the cards on the shelf now boot-up.
3.
The DTU cards should display the following LED sequence:
Note
: The boot-up procedure for these cards takes approximately 15 minutes.
a. Red LED, amber LEDs & green surface mount LEDs all ON. Green LED
FLASHING
b. Red LED ON, green LED FLASHING, amber LEDs OFF & green surface mount
LEDs showing download progress.
c. Green LED ON, green surface mount LEDs indicate card configuration as shown
below
LED
DTU
1 Top
OFF
2
OFF
3
ON
4
Bottom
OFF
The rest of the cards display the following LED sequence:
Note
: The boot-up procedure for these cards takes a couple of minutes
a. Red LED ON & green LED FLASHING
b. Green LED ON
If the cards do not boot-up correctly, i.e. any of the cards display a flashing red or
continuous red LED only, follow
the procedure in case of Card boot-up failure
Note.
Some early demo system and field trial T1 TU cards may fail to boot on initial
power up, and it may be necessary to unplug and re-insert the card to initiate the boot
sequence. If the card does not reboot then the Eprom in the card should be re-blown.
Alarm and Status Indications (Test 3)
1. Verify that the alarms and status indications (LEDs) on the system comply with those
detailed in the following tables.
Note:
The following tables are set in order of appearance on the front of the card
reading from top to bottom.
Summary of Contents for AS4000
Page 2: ......
Page 6: ...Printed Documentation 2 ...
Page 14: ...Printed Documentation 10 ...
Page 16: ...Printed Documentation 12 ...
Page 27: ...Installation 23 Typical 75ohm DDF Layout ...
Page 28: ...Printed Documentation 24 ...
Page 41: ...Installation 37 ...
Page 42: ...Printed Documentation 38 BNC Terminations to Coax ...
Page 43: ...Installation 39 Type 43 Terminations to Coax ...
Page 44: ...Printed Documentation 40 ...
Page 52: ...Printed Documentation 48 ...
Page 68: ...Printed Documentation 64 ...
Page 71: ...Installation 67 ...
Page 72: ...Printed Documentation 68 CT Rack Labelling Central Terminal Rack ...
Page 73: ...Installation 69 BNC Terminations to Coax ...
Page 74: ...Printed Documentation 70 Type 43 Terminations to Coax ...
Page 75: ...Installation 71 ...
Page 78: ...Printed Documentation 74 Card Insertion DA Rack Card Insertion Expansion Rack ...
Page 110: ...Printed Documentation 106 ...
Page 112: ...Printed Documentation 108 Combiner Shelf PSU ...
Page 133: ...Setup and Test 129 ...
Page 163: ...Setup and Test 159 ...
Page 166: ......
Page 170: ...Printed Documentation 166 ...
Page 176: ...Printed Documentation 172 ...
Page 192: ......