1. Using Sitespan create a CT rack with a dummy modem shelf.
2. From the Edit AC Shelf Properties screen assign T1-1 to the newly created CT shelf.
3. A red alarm should appear on the CTU card for the T1 activated.
4. Loopback TX to RX for the T1at the DDF. Check that the alarm clears (the amber
remote alarm is lit for several seconds before clearing).
5. Reassign the CT shelf to T1-2*, T1-3, T1-4, T1-5, T1-6, T1-7 and T1-8 in turn and
repeat steps 3 and 4.
6. Repeat steps 1 to 5 for CTUs in slots 8 and 9 if fitt
Test XTU cabling to the DDF
1. Test one XTU at a time.
2. Activate all E1s/T1s for the chosen XTU card.
3. Check that 8 red LEDs appear on the front of the card (Netspan should also indicate
the E1/T1 alarm.)
4. Loopback each E1 in turn and check that the corresponding alarm for that channel is
cleared. (Note: the amber remote alarm is illuminated for several seconds before
clearing.)
5. Remove all jumper links and disable all E1s/T1s.
6. Repeat steps 2-5 for each XTU fitted.
Connecting the AC to the Network
(this section applies only if the AC has been configured using a local Laptop PC)
1. Ensure the NMC administrator has entered all the AC shelf configuration in the
Netspan/Sitespan Server.
2. Within the AC Shelf Properties window, enter the
Port: (should be the NMC PC COM port the AC shelf is connected to)
TEI: (should be set to the pre-determined setting allocated at the planning stage)
Leave other data fields unchanged.
3.
Select OK to complete the configuration process.
4.
DISCONNECT THE LAPTOP PC CONNECTION TO THE AC SHELF AND
RECONNECT THE NMC CONNECTION TO THE SHELF.
5.
Call in the NMC and ensure the AC shelf is seen at the NMC system. From the Shelf
Object List view, the AC shelf should be in CONNECTED and DOWNLOADING state.
Connect E1s/T1s to the Switch or Cross-Connect at the DDF
1. If V5.1 interface is being used then the NMC administrator should enable the V5.1
interface. From the AC shelf equipment view, select the XTU card and use Edit-
>AS4000 DA V5.1 XTU
2. Connect the required E1s/T1s to the Switch or Cross-Connect using jumper cables at
the DDF.
3. All the E1/T1links should be enabled on Netspan at the NMC.
4. From the AC shelf equipment view, double click on the XTU card. This will open the
card view window. Check the E1/T1 connection to the switch is working; E1/T1-Loss
of Signal and E1/T1- Loss of FA alarms are cleared.
Summary of Contents for AS4000
Page 2: ......
Page 6: ...Printed Documentation 2 ...
Page 14: ...Printed Documentation 10 ...
Page 16: ...Printed Documentation 12 ...
Page 27: ...Installation 23 Typical 75ohm DDF Layout ...
Page 28: ...Printed Documentation 24 ...
Page 41: ...Installation 37 ...
Page 42: ...Printed Documentation 38 BNC Terminations to Coax ...
Page 43: ...Installation 39 Type 43 Terminations to Coax ...
Page 44: ...Printed Documentation 40 ...
Page 52: ...Printed Documentation 48 ...
Page 68: ...Printed Documentation 64 ...
Page 71: ...Installation 67 ...
Page 72: ...Printed Documentation 68 CT Rack Labelling Central Terminal Rack ...
Page 73: ...Installation 69 BNC Terminations to Coax ...
Page 74: ...Printed Documentation 70 Type 43 Terminations to Coax ...
Page 75: ...Installation 71 ...
Page 78: ...Printed Documentation 74 Card Insertion DA Rack Card Insertion Expansion Rack ...
Page 110: ...Printed Documentation 106 ...
Page 112: ...Printed Documentation 108 Combiner Shelf PSU ...
Page 133: ...Setup and Test 129 ...
Page 163: ...Setup and Test 159 ...
Page 166: ......
Page 170: ...Printed Documentation 166 ...
Page 176: ...Printed Documentation 172 ...
Page 192: ......